ASSOCIATION OF FOREST AND HUNTING WORKERS OF SERBIA"FOREST AND HUNTING " |
||||||
![]() ![]() |
|||||||
|
Completed project: The project is being
implemented in cooperation with the Hunting Association "Pek - Branicevo" Branicevo. Ministry of Environmental Protection has recognized the importance
of this project and approved funding for its co-financing, which was completed
and the Contract Number: 401-00-1626/21-03 of the day 05/10/2021. The overall objective of the project: - protection and improvement of the quality of nature by using
existing resources and renewable energy sources. Specific objectives of the project:
- providing a permanent source of water for wild and
domestic animals using solar energy;
- improving the biodiversity of the area;
- providing water for firefighting;
- promotion of the use of renewable energy sources in the
service of improving environmental conditions
Direct beneficiaries of the project, in addition to the
basic target group (wild animals):
- local community (cattle breeders);
- hunting associations;
- nature protection associations;
- Fire Service, Serbian Army, Ministry of Internal Affairs
of the Republic of Serbia;
Indirect users:
The population of the municipality of
Golubac and the peripheral area of the municipality of Golubac and Veliko Gradiste.
Estimated duration of project activities: July 15 - December 20, 2021.
Project activities:
- Field surveying and marking of places for construction of
planned facilities; - Cleaning the work surface from the existing wood material and performing rough work by hiring construction machines; - Excavation of the earth with the laying of a cistern and the connection of water supply installations; - Drilling of water wells and installation of pipes; - Installing a watering troughs for wild animals; - Construction of a concrete stand for solar panels, with the installation of a supporting pillar and protective fence; - Excavation and leveling of land ; - Mounting and installation of the solar system for a permanent watering place for wild animals; - Commissioning; - Public presentation of project results with discussion;
All project activities were completed on December 30, 2021, when the facility was handed over to a partner organization - Hunting Association "Pek - Braničevo" from Braničevo for further storage and management. |